AOA Diagram Example| Activity-On-Arrow (AOA) PERT Diagram Construction - Worked Out Example [Part-1]

Channel:
Subscribers:
3,110
Published on ● Video Link: https://www.youtube.com/watch?v=qplQPuetIUw



Duration: 13:15
1,918 views
0


This tutorial provides some worked out examples on how to construct Activity-On-Arrow (AOA) PERT Diagram given a project schedule.

Slide Link: https://drive.google.com/file/d/1uKLyBWyJ8nZbmxP6sim7sYswMX7srFzp/view?usp=sharing

#AOA
#ActivityOnArrowDiagram
#ProjectManagement




Other Videos By HodgePodge


2020-09-01Project Crashing | Discussion on Project Crashing | Project Acceleration | How to Crash a Project
2020-09-01For Loops in C Structured Programming Language|Nested For Loops in C Structured Programming Language
2020-08-18Activity-On-Arrow (AOA) PERT Diagram Construction From Project Schedule| Worked Out Example [Part-4]
2020-08-18Activity-On-Arrow (AOA) PERT Diagram Construction From Project Schedule| Worked Out Example [Part-3]
2020-08-17Significance of Total Float (TF)/Total Slack (TS) and Free Float (FF)/Free Slack (FS) in CP Analysis
2020-08-13Critical Path Analysis (CPA) using the Precedence Diagram Method (PDM) | EST, EFT, LST, LFT, TF, FF
2020-08-11Bitwise Operators in C Structured Programming Language |Bitwise AND, OR, NOT, XOR, Shifting Operator
2020-08-11Logical Operators in C Structured Programming Language | Example
2020-08-11Relational Operators in C Structured Programming Language | Example
2020-08-09GANTT Chart | Definition | Characteristics | Example | How to Construct | Advantages | Disadvantages
2020-08-08AOA Diagram Example| Activity-On-Arrow (AOA) PERT Diagram Construction - Worked Out Example [Part-1]
2020-08-08AOA Diagram Example| Activity-On-Arrow (AOA) PERT Diagram Construction - Worked Out Example [Part-2]
2020-08-06Activity-On-Node (AON) PERT Diagram Construction - Worked Out Example |How to construct AON Diagram
2020-07-27Use of Different Arithmetic Operators in C Structured Programming Language (Coding Example)
2020-07-27Arithmetic Operators in C Structured Programming Language | Use of + - * / % Arithmetic Operators
2020-07-27Operational Feasibility Analysis/Study in an Information System Design [Part-1]
2020-07-27Schedule Feasibility Analysis | Schedule Feasibility Analysis/Study in an Information System Design
2020-07-26Economic Feasibility Analysis | Economic Feasibility Analysis/Study in an Information System Design
2020-07-26Technical Feasibility Analysis | Technical Feasibility Analysis/Study in an Information System
2020-07-26Critical Path Analysis in an Activity-On-Arrow (AOA) PERT Diagram using Critical Path Method (CPM)
2020-07-25Address Operator (&) in C Programming Language | Use of Address Operator (&) in printf() and scanf()



Tags:
AOA
Construction
Activity
Arrow
PERT
Diagram
Characteristics
Scenarios
AOA PERT Diagram
Activity-On-Arrow PERT Diagram Example
how to construct aoa diagram
aoa diagram example
AOA Diagram
Activity-On-Arrow Diagram
how to draw AOA diagram
how to construct aoa chart
How to draw Activity-on-Arrow network diagram
Network Diagram Project management
AON vs AOA
Activity on node vs Activity on arrow
How to draw a CPM network diagram
CPM
aoa diagram construction
arrow
rule
aoa