Calax Project Update as of May 05, 2021
Calax Project Update as of May 05, 2021
Type of Work:
Cavite – Laguna Expressway (CALAX) Project Laguna Section
• Construction of 5km alignment (Laguna Segment) from Sta. 27+873.904 to Sta. 32+873.904
• Portland Cement Treated Plant Mix Base Course Works
• Construction of road Sta. 32+873.904 to Sta. 33+924
• Construction of Sta. Rosa Interchange Access Road
• Construction of Sta. Rosa Interchange, Sta. Rosa Overpass Bridge (OB11), Ayala Laguna Blvd., (EN13) to Tamayo Area
A construction of 5 kilometer Portland Cement Concrete Pavement road (main alignment), includes 1.032 kilometer access road from Station 00+000 to Sta. 1+032, bridges, interchange, overpass bridge, supply, labor, and laying of Portland Cement Treated Plant Mix Base Course.
Owner:
MPT South Corporation
Date Started: September 19, 2018
Target Date of Completion: June 15, 2021
Contractor:
C.M. Pancho Construction, Inc.
PCAB License No. 183 AAAA Large B
More videos here:
https://www.youtube.com/watch?v=E2UHhM3l95k&list=PL2MibvFuwoXImi06JYRTtqK7MdPElZWvo&index=2
Facebook:
https://www.facebook.com/cmpancho/
Website:
https://cmpancho.com
#CMPANCHO #CMPCI CMPancho Construction, CALAEX, CALAX, Cavite Laguna Expressway, dmitrivalencia, Pinoy Joyride, Tibig Road, Silang, Cavite, Santa Rosa, Laguna, Ayala Westgrove, Metro Pacific Tollways Corporation, Civil Engineering